For the construction of the Borkum Riffgrund 2 offshore wind farm, Cuxhaven (Germany) was selected as marshalling yard for the final assembly of 20 suction bucket jackets.  After joining the suction buckets with the upper structure, each jacket reaches 62 meters of height and weighs 950 tons.

Scope:

  • Load in of preassembled jacket parts
  • Final assembly of the jacket structure
  • Lifting jacket structure on the suction buckets
  • Local transport of the jacket parts and completed jackets
  • Load out of completed jackets

Provided services:

  • Heavy lifting
  • SPMT transports
  • Steel supports for temporary storage
  • Engineering